Export XER file with only some activities

Member for

5 years 5 months

Hi Lyna, are you trying to compare the changes between specific sections of the schedule, and ignore other sections? What information are you trying to analyze once you get the schedule into SA?

Member for

16 years 3 months

copy the project

filter for the activities that you DO NOT WANT now you are left with waht you want 

press deleted

file export xer 

remember you can not schedule THIS project as there may be ties to activites that have been deleted

Member for

21 years

You need to copy/paste what you want into a new project, and export that. You can ponly export whole projects