Wrong project name in Print preview

Member for

20 years 6 months

It'll be in the page setup for that particular layout you are using (note each layout will have different print setup). select FILE>PAGE SETUP, then HEADER/FOOTER where the project name is. Find the section that is displaying the incorrect name, and then click on "MODIFY", you can either delete the project name and type in the correct name, or enter "[project_name]" to automatically get the name from the proejct information.