How do you show productivities in P6 in a transparent way? Where do you enter such values? As far as I recal there is no such functionality in P6?
What do you mean by activities dedicated to volume of work for winter?
Activity might be delayed from winter to summer. And what when a portion falls in winter and another portion fall in summer, this make too many possibilities. Using separate activities may not be a good idea.
Best Regards
Rafael
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Mon, 2020-05-18 21:04
Member for
21 years 8 monthsPlease click the following
Please click the following link to download presentation pdf.
Link to Quantities_Workloads_and_Production_Rates.pdf/file
Best Regard,
Rafael Davila
Member for
16 years 3 monthsput the resources on a
put the resources on a different calendar
Member for
21 years 8 monthsDejan:How do you show
Dejan:
How do you show productivities in P6 in a transparent way? Where do you enter such values? As far as I recal there is no such functionality in P6?
What do you mean by activities dedicated to volume of work for winter?
Activity might be delayed from winter to summer. And what when a portion falls in winter and another portion fall in summer, this make too many possibilities. Using separate activities may not be a good idea.
Best Regards
Rafael
Member for
21 years 8 months(No subject)
Member for
15 years 11 monthsUse the REsource Detail:
Use the REsource Detail: Effectivity and Max Unit per Time
Set the Reduced Max Qty (Max Unit per Time) within the Effective dates.