Showing productivity changes with different Resource Calendars

Member for

16 years 3 months

put the resources on a different calendar 

Member for

21 years 8 months

Dejan:

How do you show productivities in P6 in a transparent way? Where do you enter such values? As far as I recal there is no such functionality in P6?

What do you mean by activities dedicated to volume of work for winter?

Activity might be delayed from winter to summer. And what when a portion falls in winter and another portion fall in summer, this make too many possibilities. Using separate activities may not be a good idea.

Best Regards

Rafael

Member for

21 years 8 months

Member for

15 years 11 months

Use the REsource Detail: Effectivity and Max Unit per Time

Set the Reduced Max Qty (Max Unit per Time) within the Effective dates.