whne you say retire completed I do not know what you mean ? I also do not know what a non performed actviities are
if you mean the activities are no longer in the scope then I would should show the same actual start and finish date equal to the date that you were told that this activity is not longer in the scope.
PUtting 1 day duration WILL make them critical making them complted will not
I would also assign an activity code theses and make a comment in the notes tab. This way you can filter and gropu these if need be.
Member for
16 years 3 monthsGlad I could help
Glad I could help
Member for
11 years 6 monthsThanks for the detailed
Thanks for the detailed explanation Zoltan. it makes sense.
Member for
16 years 3 monthsan actviity can be in one of
an actviity can be in one of 4 categories
not started
in progress
completed
modified in progress using suspend and resume
whne you say retire completed I do not know what you mean ? I also do not know what a non performed actviities are
if you mean the activities are no longer in the scope then I would should show the same actual start and finish date equal to the date that you were told that this activity is not longer in the scope.
PUtting 1 day duration WILL make them critical making them complted will not
I would also assign an activity code theses and make a comment in the notes tab. This way you can filter and gropu these if need be.