Primavera WBS as PDF

Member for

16 years 3 months

glad we could help

Member for

7 years 7 months

Thank you Alexandre'

Thank you Zoltan,

It works very well.

Member for

16 years 3 months

no but in p6 select wbs on the left

then uptop on the command bar slect chart view

now you can print a pdf of this 

or take a screen shot and paste inot power pooint

Member for

22 years 9 months

Hello Mohammed,

Display the WBS, then click the "View as chart" icon in the toolbar (count 8 buttons from the left)

Click File, Print preview, then use the Print option to set the printing as needed

Select your pdf printer; I am working with Foxitreader, a very efficient reader and printer for pdf files

I hope this will help you

Alexandre

Member for

7 years 7 months

Hi Zoltan,

Thank you for your reply.

After exporting the wbs to Excel, It will be as a table and not as a chart.

It can be drawn as a chart only manual or there is another method.

Member for

16 years 3 months

2 optons just print as pdf in p6

or copy the wbs and paste inot excel and make a pdf there

Member for

7 years 7 months

Hi Raymund,

Thank you for your reply.

With appreciation,

Member for

15 years 11 months

Hi,

Use the doPdf Printer

 

 

Regards.