Oracle Primavera - PM6 Member for 20 years 6 months Member for 20 years 7 months Submitted by Santosh Bhat on Fri, 2020-05-01 01:41 Permalink 1) Use a Global Activity code 1) Use a Global Activity code or a UDF to flag all those milestones in each project. 2) Open all the projects - you can do this by opening an entire project node in projects view 3) Create a filter that selects only activities that have been flagged in 1) above 4) Group your activity layout to by EPS/WBS and tick the option Show Summaries Only 5) Use colours/fonts of the grouping bands to achieve the look you want and save this Activity layout. Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Thu, 2020-04-30 23:04 Permalink You may use UDF. You may use UDF. Log in or register to post comments
Member for 20 years 6 months Member for 20 years 7 months Submitted by Santosh Bhat on Fri, 2020-05-01 01:41 Permalink 1) Use a Global Activity code 1) Use a Global Activity code or a UDF to flag all those milestones in each project. 2) Open all the projects - you can do this by opening an entire project node in projects view 3) Create a filter that selects only activities that have been flagged in 1) above 4) Group your activity layout to by EPS/WBS and tick the option Show Summaries Only 5) Use colours/fonts of the grouping bands to achieve the look you want and save this Activity layout.
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Thu, 2020-04-30 23:04 Permalink You may use UDF. You may use UDF.
Member for
20 years 6 months1) Use a Global Activity code
1) Use a Global Activity code or a UDF to flag all those milestones in each project.
2) Open all the projects - you can do this by opening an entire project node in projects view
3) Create a filter that selects only activities that have been flagged in 1) above
4) Group your activity layout to by EPS/WBS and tick the option Show Summaries Only
5) Use colours/fonts of the grouping bands to achieve the look you want and save this Activity layout.
Member for
15 years 11 monthsYou may use UDF.
You may use UDF.