copy the current schedule and desatsus it to remove the progress and set the data date back to the originla start date of the project
How to de-status a schedule
1. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units to Original
2. Choose View, Columns and add the columns for Actual Labor Units, Actual Nonlabor Units.
3. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule. To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and note the Planned Start date.
4. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.
5. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.
6. Choose Tools, Global Change and run the 1st Global Change. This will set the Actual Material Units to zero.
7. Run the 2nd global change which sets the activity status to Not Started
1st Global Change
Subject Area:
Activity Resource Assignments
Where Resource Type equals Material
Then Actual Material Units = 0
2nd Global Change
Subject Area:
Activities
Where Activity Status is not equal to Not Started
Then Activity Status = Not Started
If this process is not used you may encounter the following error:
"Cannot set status to Not Started if activity has actuals."
3rd Global Change
Change duration to activities by running global change for Not Started activities
Subject Area:
Activities
Where Activity Status is not equal to Not Started
Then Remaining Duration = Original Duration
Change the data date to the project start date and recalcuate the schedule
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Thu, 2020-04-30 23:16
1. Redo copying the old schedule but make sure include baseline.
2. From the copy, restore the baseline.
3. Assign the restored baseline into the updated schedule.
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Thu, 2020-04-30 19:44
Member for
16 years 3 monthscopy the current schedule and
copy the current schedule and desatsus it to remove the progress and set the data date back to the originla start date of the project
How to de-status a schedule
1. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units to Original
2. Choose View, Columns and add the columns for Actual Labor Units, Actual Nonlabor Units.
3. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule. To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and note the Planned Start date.
4. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.
5. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.
6. Choose Tools, Global Change and run the 1st Global Change. This will set the Actual Material Units to zero.
7. Run the 2nd global change which sets the activity status to Not Started
1st Global Change
Subject Area:
Activity Resource Assignments
Where Resource Type equals Material
Then Actual Material Units = 0
2nd Global Change
Subject Area:
Activities
Where Activity Status is not equal to Not Started
Then Activity Status = Not Started
If this process is not used you may encounter the following error:
"Cannot set status to Not Started if activity has actuals."
3rd Global Change
Change duration to activities by running global change for Not Started activities
Subject Area:
Activities
Where Activity Status is not equal to Not Started
Then Remaining Duration = Original Duration
Change the data date to the project start date and recalcuate the schedule
Member for
15 years 11 months1. Redo copying the old
1. Redo copying the old schedule but make sure include baseline.
2. From the copy, restore the baseline.
3. Assign the restored baseline into the updated schedule.
Member for
22 years 9 monthsHI Martin,Restore the
HI Martin,
Restore the baseline of project A; baseline will become a new independant project (A1)
Copy project A1 as A2 if you want to re-baseline project A afterwards
Open project B, then use the project A1 as the baseline
Alexandre