Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2020-04-27 13:32 Permalink glad I could help glad I could help Member for 5 years 6 months Member for 5 years 6 months Submitted by troon on Fri, 2020-04-24 17:01 Permalink Thanks Zoltan Thanks Zoltan Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2020-04-24 13:19 Permalink open your project go to the open your project go to the PROJECTS directory click on the calclations tab make dure that Recalculate Actual Units and costs when duration % complete changes is NOT checked Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2020-04-27 13:32 Permalink glad I could help glad I could help
Member for 5 years 6 months Member for 5 years 6 months Submitted by troon on Fri, 2020-04-24 17:01 Permalink Thanks Zoltan Thanks Zoltan
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2020-04-24 13:19 Permalink open your project go to the open your project go to the PROJECTS directory click on the calclations tab make dure that Recalculate Actual Units and costs when duration % complete changes is NOT checked
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
5 years 6 monthsThanks Zoltan
Thanks Zoltan
Member for
16 years 3 monthsopen your project go to the
open your project
go to the PROJECTS directory
click on the calclations tab make dure that Recalculate Actual Units and costs when duration % complete changes is NOT checked