Using different software we create the fragnet file from scratch or from an existing project file. Then we use Insert project as a new phase to copy the fragnet into our impacted schedule. Resources, Materials, Cost components, Calendars, weeks, exceptions as well as links within the selected WBS will be copied. If activity codes are not used within target schedule they will be copied without any change.
The concept of Fragnets doesn’t exist anymore in P6. It is a feature in P3. In a P3 fragnet, a user can store a set of activities along with their full details such as relationships, codes, costs, resources, etc. and use this stored set to be pasted as an entire group in any number of places with a single click, without having to create the same set again and again. This saved immense time and efforts. One way to do this in P6 is to replicate an entire WBS (or more) and the constituent activities will also be replicated with all the details. If this is supposed to be done across projects, you have to open multiple projects at the same time.
Best Regards, Rafael
Member for
19 years 1 month
Member for19 years1 month
Submitted by Thomas Nicholson on Mon, 2020-10-19 16:00
at the Project level go to defaults and make sure that in the auto-numbering section that increament activiy ID based on selected activity IS NOT CHECKED
Member for
19 years 1 month
Member for19 years1 month
Submitted by Thomas Nicholson on Mon, 2020-10-19 11:49
Member for
11 years 4 monthsHi Thomas,I normally do it
Hi Thomas,
I normally do it this way.
Let's say I want to copy a WBS from Project File A to Project File B.
Video detailing the drag technique in Step 3 can be seen in this link https://imgur.com/MsJmiKw
Member for
16 years 3 monthsdod you try doing it while in
dod you try doing it while in the WBS section NOT the activity section ?
Member for
21 years 8 monthsUsing different software we
Delay analysts do this every day. It is common when performing basic TIA.
Can you insert a fragnet (separate project schedule) into another project schedule in Primavera P6? – Project Scheduling & Management Consulting
The concept of Fragnets doesn’t exist anymore in P6. It is a feature in P3. In a P3 fragnet, a user can store a set of activities along with their full details such as relationships, codes, costs, resources, etc. and use this stored set to be pasted as an entire group in any number of places with a single click, without having to create the same set again and again. This saved immense time and efforts. One way to do this in P6 is to replicate an entire WBS (or more) and the constituent activities will also be replicated with all the details. If this is supposed to be done across projects, you have to open multiple projects at the same time.
Best Regards, Rafael
Member for
19 years 1 monthHi Zoltan, Neither original
Hi Zoltan,
Neither original nor the project I'm copying into have that box checked. It's fine if I use cut and paste but not copy.
I have a work around but surely it shouldn't matter if it's an empty project there's no need to renumber anything.
thanks for your help as always.
Thom
Member for
16 years 3 monthsat the Project level go to
at the Project level go to defaults and make sure that in the auto-numbering section that increament activiy ID based on selected activity IS NOT CHECKED
Member for
19 years 1 monthHi all, This is still a
Hi all,
This is still a problem, simple copy of a WBS structure and all it's activities to a new project but keeping the activity ID's.
I'm using the WBS pane to copy them over but it insists on renumbering for no reason. Under group and sort I seem to have every option but EPS.
I'm sure this used to be a simple operation.
Any help or advice would be gratefully received.
Thanks,
Thom
Member for
19 years 1 monthHi Raymund, That's exactly
Hi Raymund,
That's exactly what I'm doing which is why I was confused when it changed all my activity IDs.
thanks,
Member for
16 years 3 monthsalso make sure that at the
also make sure that at the project level that under group and sort it is set to EPS
Member for
15 years 11 monthsHi.Open both Schedule, in WBS
Hi.
Open both Schedule, in WBS pane copy the WBS from 1 Schedule to another. The ACT ID shall be the same from both.
Regards.