Changing activity start/finish date and duration after being baselined

Member for

15 years 11 months

Hi.

Make Sure that Planned Dates = Current Dates, Do this in Global Change.

 

Regards.

Member for

5 years 6 months

Thanks Alexandre !!

Member for

22 years 9 months

Hello,

Go to Project, Assign baseline; remove the baseline from Project Baseline and User Baselines when necessay

Go to Project, Update baseline; select the baseline and click Restore to convert the baseline into a new independant project

Open this project, and edit the activity you are mentionning, then re-schedule the project

Open the "current"project again, P6 will close the "new" project

Go to Project, Update baseline; click Add, select the second option and use the "new" project as the baseline for the "current" project

Take care, Stay home

Alexandre