Oracle Primavera - PM6 Member for 12 years Member for 12 years Submitted by cmw45750 on Fri, 2020-04-03 14:40 Permalink We have users regularly We have users regularly hitting F10 to commit changes I have a few users on Citrix but most log in through client. We use a networked Oracle database. My IT people keep referencing tables being "locked" by users. None of them have exclusive rights. Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2020-04-03 14:17 Permalink tell them to periodically tell them to periodically press F10 which is commit changes or select file commit changes My guess that this is on a citrix server or some remote location on local to the hard drive. Log in or register to post comments
Member for 12 years Member for 12 years Submitted by cmw45750 on Fri, 2020-04-03 14:40 Permalink We have users regularly We have users regularly hitting F10 to commit changes I have a few users on Citrix but most log in through client. We use a networked Oracle database. My IT people keep referencing tables being "locked" by users. None of them have exclusive rights.
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2020-04-03 14:17 Permalink tell them to periodically tell them to periodically press F10 which is commit changes or select file commit changes My guess that this is on a citrix server or some remote location on local to the hard drive.
Member for
12 yearsWe have users regularly
We have users regularly hitting F10 to commit changes
I have a few users on Citrix but most log in through client. We use a networked Oracle database.
My IT people keep referencing tables being "locked" by users. None of them have exclusive rights.
Member for
16 years 3 monthstell them to periodically
tell them to periodically press F10 which is commit changes or select file commit changes
My guess that this is on a citrix server or some remote location on local to the hard drive.