NAN & INF

Member for

16 years 3 months

WRONG 100% WRONG !

budgeted units will NOT chnage if duration is changed (if i change to fixed duration & units/time).  

hence the word FIXED DURATION & UNITS/time

Member for

12 years 8 months

Thank you Engr. Zoltan. Unfortunately, I dont want to mess my other data as this will cause changes to budgeted units whenever duration is changed (if i change to fixed duration & units/time).  Is there any other way? I guess keeping the resource curve to default will help. I don't know if I am correct. Appreciate your help.

Member for

16 years 3 months

change the duration type to fixed duration & units/time. You can add a column for duration type do the first one then doa fill down

also in the PROJECTS directory under the Resources tab uncheck drive activity dates by default