Thank you Engr. Zoltan. Unfortunately, I dont want to mess my other data as this will cause changes to budgeted units whenever duration is changed (if i change to fixed duration & units/time). Is there any other way? I guess keeping the resource curve to default will help. I don't know if I am correct. Appreciate your help.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2020-04-02 13:27
Member for
16 years 3 monthsWRONG 100% WRONG !budgeted
WRONG 100% WRONG !
budgeted units will NOT chnage if duration is changed (if i change to fixed duration & units/time).
hence the word FIXED DURATION & UNITS/time
Member for
12 years 8 monthsThank you Engr. Zoltan.
Thank you Engr. Zoltan. Unfortunately, I dont want to mess my other data as this will cause changes to budgeted units whenever duration is changed (if i change to fixed duration & units/time). Is there any other way? I guess keeping the resource curve to default will help. I don't know if I am correct. Appreciate your help.
Member for
16 years 3 monthschange the duration type to
change the duration type to fixed duration & units/time. You can add a column for duration type do the first one then doa fill down
also in the PROJECTS directory under the Resources tab uncheck drive activity dates by default