Earned Value / Baseline Issue

Member for

20 years 6 months

EV is the budgeted cost for work performed = budget cost  x  n%

P6 take the budget from the assigned baseline, since activity X is not in baseline 1 , so there is no budget for activity X.

that is why P6 did not calculate the EV for activity X

Member for

15 years 7 months

WI,

 

P6 will calcualte EV based on what is selected under 'Assign Basline' menu.

1. if current project is selected then EV of Activity X will be calcualted.

2. if 'Baseline project is selected then EV of Activity will be zero

 

Member for

15 years 7 months

WI,

 

P6 will calcualte EV based on what is selected under 'Assign Basline' menu.

1. if current project is selected then EV of Activity X will be calcualted.

2. if 'Baseline project is selected then EV of Activity will be zero