Oracle Primavera - PM6 Member for 20 years 6 months Member for 20 years 7 months Submitted by Zhang Haixiang on Wed, 2020-03-04 01:24 Permalink EV is the budgeted cost for EV is the budgeted cost for work performed = budget cost x n% P6 take the budget from the assigned baseline, since activity X is not in baseline 1 , so there is no budget for activity X. that is why P6 did not calculate the EV for activity X Member for 15 years 7 months Member for 15 years 7 months Submitted by Rashid Iqbal on Tue, 2020-03-03 19:06 Permalink WI, P6 will calcualte EV WI, P6 will calcualte EV based on what is selected under 'Assign Basline' menu. 1. if current project is selected then EV of Activity X will be calcualted. 2. if 'Baseline project is selected then EV of Activity will be zero Member for 15 years 7 months Member for 15 years 7 months Submitted by Rashid Iqbal on Tue, 2020-03-03 19:06 Permalink WI, P6 will calcualte EV WI, P6 will calcualte EV based on what is selected under 'Assign Basline' menu. 1. if current project is selected then EV of Activity X will be calcualted. 2. if 'Baseline project is selected then EV of Activity will be zero Log in or register to post comments
Member for 20 years 6 months Member for 20 years 7 months Submitted by Zhang Haixiang on Wed, 2020-03-04 01:24 Permalink EV is the budgeted cost for EV is the budgeted cost for work performed = budget cost x n% P6 take the budget from the assigned baseline, since activity X is not in baseline 1 , so there is no budget for activity X. that is why P6 did not calculate the EV for activity X
Member for 15 years 7 months Member for 15 years 7 months Submitted by Rashid Iqbal on Tue, 2020-03-03 19:06 Permalink WI, P6 will calcualte EV WI, P6 will calcualte EV based on what is selected under 'Assign Basline' menu. 1. if current project is selected then EV of Activity X will be calcualted. 2. if 'Baseline project is selected then EV of Activity will be zero
Member for 15 years 7 months Member for 15 years 7 months Submitted by Rashid Iqbal on Tue, 2020-03-03 19:06 Permalink WI, P6 will calcualte EV WI, P6 will calcualte EV based on what is selected under 'Assign Basline' menu. 1. if current project is selected then EV of Activity X will be calcualted. 2. if 'Baseline project is selected then EV of Activity will be zero
Member for
20 years 6 monthsEV is the budgeted cost for
EV is the budgeted cost for work performed = budget cost x n%
P6 take the budget from the assigned baseline, since activity X is not in baseline 1 , so there is no budget for activity X.
that is why P6 did not calculate the EV for activity X
Member for
15 years 7 monthsWI, P6 will calcualte EV
WI,
P6 will calcualte EV based on what is selected under 'Assign Basline' menu.
1. if current project is selected then EV of Activity X will be calcualted.
2. if 'Baseline project is selected then EV of Activity will be zero
Member for
15 years 7 monthsWI, P6 will calcualte EV
WI,
P6 will calcualte EV based on what is selected under 'Assign Basline' menu.
1. if current project is selected then EV of Activity X will be calcualted.
2. if 'Baseline project is selected then EV of Activity will be zero