if my memory serves me right; first install the Java and Oracle and then start the installation of P6. If you find in google there are few who have docuemnted step by step installation.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Wed, 2020-03-04 13:16
Member for
5 years 8 monthsIf you have a licensed copy
If you have a licensed copy currently under support, create a service request at support.oracle.com. One of the engineers can assist.
All ORA errors in P6 are thrown from the database. In this case the database is saying that the username and password you are entering is not valid.
Member for
15 years 7 monthsAmir,if my memory serves me
Amir,
if my memory serves me right; first install the Java and Oracle and then start the installation of P6. If you find in google there are few who have docuemnted step by step installation.
Member for
16 years 3 monthstry thisEdit the Existing
try this
Edit the Existing Configuration
Member for
9 years 10 monthsdear sir, I tried but again
dear sir,
I tried but again failed. Could you please share contact info to send captures ı get. I need help.
regards,
Amir.
Member for
9 years 10 monthsdear sir, I tried but again
dear sir,
I tried but again failed. Could you please share contact info to send captures ı get. I need help
Member for
16 years 3 monthstry this in the setupFor the
try this in the setup
For the Oracle Connection String, type XE
For username, type pubprm$pm
For password, type <this was defined during installation > try admin1