Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2020-02-19 13:42 Permalink ok u can do that make another ok u can do that make another one and giving it the format of text Member for 5 years 9 months Member for 5 years 9 months Submitted by jnnilesh29 on Tue, 2020-02-18 17:14 Permalink Sorry for the formating Sorry for the formating problem but using Text UDF and in glocal change selecting '&' Operator and '%' Parameter/Value will work. Member for 5 years 9 months Member for 5 years 9 months Submitted by jnnilesh29 on Tue, 2020-02-18 17:12 Permalink Hi Zoltan, Thanks for your Hi Zoltan, Thanks for your help. I have found the solution to get % symbol/sign and I hope this could help to other people who might be looking for the solution. 1. Create another UDF: Data Type Text (Call it % Progressed for this Period) 2. Global Change: Then Parameter Is Parameter/Value Operator Parameter/Value % Progressed for this Period = UDF (Choose UDF you want to & % (Created in Step 1) insert % sign) 3. Apply Changes-> Commit Changes 4. Insert UDF from Column and you will see % sign with number. Done! Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2020-02-17 13:44 Permalink no just change the heading at no just change the heading at the top of the udf column Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2020-02-19 13:42 Permalink ok u can do that make another ok u can do that make another one and giving it the format of text
Member for 5 years 9 months Member for 5 years 9 months Submitted by jnnilesh29 on Tue, 2020-02-18 17:14 Permalink Sorry for the formating Sorry for the formating problem but using Text UDF and in glocal change selecting '&' Operator and '%' Parameter/Value will work.
Member for 5 years 9 months Member for 5 years 9 months Submitted by jnnilesh29 on Tue, 2020-02-18 17:12 Permalink Hi Zoltan, Thanks for your Hi Zoltan, Thanks for your help. I have found the solution to get % symbol/sign and I hope this could help to other people who might be looking for the solution. 1. Create another UDF: Data Type Text (Call it % Progressed for this Period) 2. Global Change: Then Parameter Is Parameter/Value Operator Parameter/Value % Progressed for this Period = UDF (Choose UDF you want to & % (Created in Step 1) insert % sign) 3. Apply Changes-> Commit Changes 4. Insert UDF from Column and you will see % sign with number. Done!
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2020-02-17 13:44 Permalink no just change the heading at no just change the heading at the top of the udf column
Member for
16 years 3 monthsok u can do that make another
ok u can do that make another one and giving it the format of text
Member for
5 years 9 monthsSorry for the formating
Sorry for the formating problem but using Text UDF and in glocal change selecting '&' Operator and '%' Parameter/Value will work.
Member for
5 years 9 monthsHi Zoltan, Thanks for your
Hi Zoltan,
Thanks for your help. I have found the solution to get % symbol/sign and I hope this could help to other people who might be looking for the solution.
1. Create another UDF: Data Type Text (Call it % Progressed for this Period)
2. Global Change:
Then Parameter Is Parameter/Value Operator Parameter/Value
% Progressed for this Period = UDF (Choose UDF you want to & %
(Created in Step 1) insert % sign)
3. Apply Changes-> Commit Changes
4. Insert UDF from Column and you will see % sign with number.
Done!
Member for
16 years 3 monthsno just change the heading at
no just change the heading at the top of the udf column