if you want you can have a resource for the materail and a separate resource for the labor to install it. That is up to you as to how you plan to track this item.

you do not have to divide the budgeted amoint by the number of days the program will do this for you.

If it was me I would create a resource called lumpsum and assign the total budgeted cost for this activity to the the resource

Member for

5 years 9 months

Hi Mr. Zoltan,

 

For the excavation,should I assign it as a material resource and assign the budget?

 

And for the budget, example the total budgeted amount is USD100M, how will I compute for the budget cost? Should I divide it by time and days?

Member for

16 years 3 months

add a resource then assign the resource to each activity then assign a budgeted cost to each actviity using the resource.

Member for

5 years 9 months

Hi Mr. Zoltan,

 

How will I place the budget? How am I suppose to incorporate that?

 

I can't create an s-curve without putting in my resources, right?

Member for

16 years 3 months

view show on bottom resource usage profile then in the lower right section rigth click and select Resource Usage Profile options and on the data tab select Cost