Rogue Activity in P6 program

Member for

16 years 3 months

glad I could help you.

Finding the anomolies and what is common among the activities that are casuing problems is always a good way to find the root of the problem.

Member for

15 years 10 months

Thanks Zoltan for the reply.  All the logic is fine.  There is however a difference in the Curve settings.  Interestingly the problem activity is the only one with a curve assigned (linear).  When I removed this selection the problem resolved itself.....

Member for

15 years 10 months

Thanks David,  I could delete & re-add, but as I rarely get data issues with P6 I like to know what is happening and why.

Member for

16 years 3 months

try to look for the anomoily for this activity see whats is commom among these activiites 

if it is a LOE it wil be geeting the actauls from the activities that it is summarizing.

a LOE should have a SS predcessor and a FF successor

also a LOE should have a curve assigned to it or it will stack all of the resources on the data date