Oracle Primavera - PM6 Member for 15 years 9 months Member for 15 years 9 months Submitted by Johannes Vandenberg on Wed, 2020-01-29 17:44 Permalink Hi YaronPerfectely explained Hi Yaron Perfectely explained by Zoltan & Santosh. If you like to see more check out this screen caputure. Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2020-01-29 13:44 Permalink you will have to assign the you will have to assign the proper wbs after importing the activities Member for 20 years 6 months Member for 20 years 7 months Submitted by Santosh Bhat on Wed, 2020-01-29 00:38 Permalink Excel import.Within P6, Excel import. Within P6, create a single activity, then FILE>EXPORT>XLS>ACTIVITIES> and set a locaton and file name to export to. Open this file in Excel, then use the single activity as a template and populate the remaining rows. Save and close the xls file. Back in P6 FILE>IMPORT>XLS and point to the saved xls file and you should have a list of activities to work with. Log in or register to post comments
Member for 15 years 9 months Member for 15 years 9 months Submitted by Johannes Vandenberg on Wed, 2020-01-29 17:44 Permalink Hi YaronPerfectely explained Hi Yaron Perfectely explained by Zoltan & Santosh. If you like to see more check out this screen caputure.
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2020-01-29 13:44 Permalink you will have to assign the you will have to assign the proper wbs after importing the activities
Member for 20 years 6 months Member for 20 years 7 months Submitted by Santosh Bhat on Wed, 2020-01-29 00:38 Permalink Excel import.Within P6, Excel import. Within P6, create a single activity, then FILE>EXPORT>XLS>ACTIVITIES> and set a locaton and file name to export to. Open this file in Excel, then use the single activity as a template and populate the remaining rows. Save and close the xls file. Back in P6 FILE>IMPORT>XLS and point to the saved xls file and you should have a list of activities to work with.
Member for
15 years 9 monthsHi YaronPerfectely explained
Hi Yaron
Perfectely explained by Zoltan & Santosh. If you like to see more check out this screen caputure.
Member for
16 years 3 monthsyou will have to assign the
you will have to assign the proper wbs after importing the activities
Member for
20 years 6 monthsExcel import.Within P6,
Excel import.
Within P6, create a single activity, then FILE>EXPORT>XLS>ACTIVITIES> and set a locaton and file name to export to.
Open this file in Excel, then use the single activity as a template and populate the remaining rows. Save and close the xls file.
Back in P6 FILE>IMPORT>XLS and point to the saved xls file and you should have a list of activities to work with.