I have tried this method, but following are the gliches that I came across and there this has not given me the accurate results:
1. Physical percentage doesn't change to zero, however, it remains the same as compared to the original schedule.
2. The global change removes the actuals of activities that are started earlier than July 2018 (that is becuase they might be completed between July 2018 to December 2018). However I want to capture the progress of activities started before July 2018.
I hope my explanation has lucid to understand the gliches in this method.
Do you have any other idea?
Looking forward to hearing from you.
Regards,
Nilesh Jain
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2020-01-23 13:21
1. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units to Original1.
2. create a filter
any
where actual start is within the range (low value) July 1, 2018 (high value) December 31, 2018
or
where actual finish is within the range (low value) July 1, 2018 (high value) December 31, 2018
2. Choose View, Columns and add the columns for Actual Labor Units, Actual Nonlabor Units.
3. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities in this column and choose Edit, Fill Down
4. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.
5. run a global change
1st Global Change
Subject Area:
Activities
all
where actual start is within the range (low value) July 1, 2018 (high value) December 31, 2018Where
and
where
Activity Status is not equal to Not Started
Then Activity Status = Not Started
6. run another global change
2nd Global Change
Subject Area:
Activities
all
where actual finish is within the range (low value) July 1, 2018 (high value) December 31, 2018
Member for
16 years 3 monthsglad I could help you
glad I could help you
Member for
16 years 3 monthsglad I could help you
glad I could help you
Member for
5 years 9 monthsAwesome. It worked.Thanks for
Awesome. It worked.
Thanks for your help again.
Member for
16 years 3 months1. run the filter again annd
1. run the filter again annd acolumn for physical % complete do the 1st one set it to 0 and then do a fill down
when you run the gloabl change also include the filter in the parapaters in the globla change if the start and end dates
Member for
5 years 9 monthsHI Zoltane, I have tried this
HI Zoltane,
I have tried this method, but following are the gliches that I came across and there this has not given me the accurate results:
1. Physical percentage doesn't change to zero, however, it remains the same as compared to the original schedule.
2. The global change removes the actuals of activities that are started earlier than July 2018 (that is becuase they might be completed between July 2018 to December 2018). However I want to capture the progress of activities started before July 2018.
I hope my explanation has lucid to understand the gliches in this method.
Do you have any other idea?
Looking forward to hearing from you.
Regards,
Nilesh Jain
Member for
16 years 3 months1. Choose Enterprise,
1. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units to Original1.
2. create a filter
any
where actual start is within the range (low value) July 1, 2018 (high value) December 31, 2018
or
where actual finish is within the range (low value) July 1, 2018 (high value) December 31, 2018
2. Choose View, Columns and add the columns for Actual Labor Units, Actual Nonlabor Units.
3. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities in this column and choose Edit, Fill Down
4. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.
5. run a global change
1st Global Change
Subject Area:
Activities
all
where actual start is within the range (low value) July 1, 2018 (high value) December 31, 2018Where
and
where
Activity Status is not equal to Not Started
Then Activity Status = Not Started
6. run another global change
2nd Global Change
Subject Area:
Activities
all
where actual finish is within the range (low value) July 1, 2018 (high value) December 31, 2018
Where
and
Activity Status is not equal to Not Started
Then Activity Status = Not Started