Oracle Primavera - PM6 Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2019-12-19 15:11 Permalink Hi Robert,You should check Hi Robert, You should check the Project Details, Resources: is the "Drive activity/task dates by default" activated or not? If not, resources may work longer than the task duration Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2019-12-19 15:11 Permalink Hi Robert,You should check Hi Robert, You should check the Project Details, Resources: is the "Drive activity/task dates by default" activated or not? If not, resources may work longer than the task duration Alexandre
Member for
22 years 9 monthsHi Robert,You should check
Hi Robert,
You should check the Project Details, Resources: is the "Drive activity/task dates by default" activated or not?
If not, resources may work longer than the task duration
Alexandre