Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2019-12-09 13:22 Permalink put in the actual then adjust put in the actual then adjust the at completion make it equal the budgted costs Member for 6 years 4 months Member for 6 years 4 months Submitted by saikrishna raju on Mon, 2019-12-09 05:27 Permalink i Checked it is Clicked even i Checked it is Clicked even then, At completion Cost Is more than Budgeted Cost Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2019-12-06 18:14 Permalink go to Projects click on the go to Projects click on the calculations tab on the rigth under resource assignments make sure that under When updating actual Units or Costs that Subtract Actual from At Completion is checked Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2019-12-09 13:22 Permalink put in the actual then adjust put in the actual then adjust the at completion make it equal the budgted costs
Member for 6 years 4 months Member for 6 years 4 months Submitted by saikrishna raju on Mon, 2019-12-09 05:27 Permalink i Checked it is Clicked even i Checked it is Clicked even then, At completion Cost Is more than Budgeted Cost
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2019-12-06 18:14 Permalink go to Projects click on the go to Projects click on the calculations tab on the rigth under resource assignments make sure that under When updating actual Units or Costs that Subtract Actual from At Completion is checked
Member for
16 years 3 monthsput in the actual then adjust
put in the actual then adjust the at completion make it equal the budgted costs
Member for
6 years 4 monthsi Checked it is Clicked even
i Checked it is Clicked even then, At completion Cost Is more than Budgeted Cost
Member for
16 years 3 monthsgo to Projects click on the
go to Projects click on the calculations tab on the rigth under resource assignments
make sure that under
When updating actual Units or Costs that
Subtract Actual from At Completion is checked