Resource Assignment

Member for

16 years 3 months

if it a a LOE it will stack it on the 1st day unless you assign a curve to it

Member for

14 years 9 months

Hi, 

 

Thank you for the reply. i checked, it was set to Day. It doesnt show the resource on day on resource assignment tho

 

[[wysiwyg_imageupload:7170:]]

 

Many thanks

Mike

Member for

15 years 11 months

Hi, set the resource analysis to daily in the user preferences.