The Performance % complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule which depends on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of, the activities planned worth has been earned so far.
Having something quantifiable and measurable is always the best way to measure progress that could be manhours or commodities such as LF of conduit ect.
Performance Percent Complete for the activity is based on Units Percent Complete. Activities without a Resource curve assigned to one or more of the Resource Assignments will use the Activity percent complete
Member for
16 years 3 monthsyou have 3 choices to
you have 3 choices to calculate earned value
Budgeted value with planned dates
At completeion with current dates
Budgeted value with current dates
Member for
6 years 5 monthsZoltan, Thanks for the
Zoltan,
Thanks for the information. I have assigned the baseline. I have not had this problem before when I've added manhours and resource loaded a schedule.
Member for
16 years 3 monthsdo you have baselin
do you have baselin attached?
if so in the Admin
Admin Preferences
Earned value
Earned Value Calculations
select Budgeted value with current dates
FYI
The Performance % complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule which depends on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of, the activities planned worth has been earned so far.
Having something quantifiable and measurable is always the best way to measure progress that could be manhours or commodities such as LF of conduit ect.
Performance Percent Complete for the activity is based on Units Percent Complete. Activities without a Resource curve assigned to one or more of the Resource Assignments will use the Activity percent complete