Performance % Complete showing 0%

Member for

16 years 3 months

you have 3 choices to calculate earned value 

Budgeted value with planned dates

At completeion with current dates 

Budgeted value with current dates

Member for

6 years 5 months

Zoltan, 

 

Thanks for the information. I have assigned the baseline. I have not had this problem before when I've added manhours and resource loaded a schedule. 

Member for

16 years 3 months

do you have baselin attached? 

if so in the Admin

Admin Preferences

Earned value

Earned Value Calculations

select Budgeted value with current dates

FYI

The Performance % complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule which depends on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of, the activities planned worth has been earned so far.

Having something quantifiable and measurable is always the best way to measure progress that could be manhours or commodities such as LF of conduit ect.

Performance Percent Complete for the activity is based on Units Percent Complete. Activities without a Resource curve assigned to one or more of the Resource Assignments will use the Activity percent complete