You can use XLS IMPORT to populate a Text User Defined Field with the new ID's you want to use, then run a Global Change to replace the ID's with the values in the UDF. Just make sure all the UDF values are unique.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2019-09-05 13:34
Member for
20 years 6 monthsYou can use XLS IMPORT to
You can use XLS IMPORT to populate a Text User Defined Field with the new ID's you want to use, then run a Global Change to replace the ID's with the values in the UDF. Just make sure all the UDF values are unique.
Member for
16 years 3 monthsyou will lhave to add the
you will lhave to add the sequence into consideration in the global change