R15.1 - You already have the maximum number of databases configured

Member for

16 years 3 months

glad that I could help there is always a work around

Member for

16 years 3 months

glad that I could help there is always a work around

Member for

6 years 2 months

Thanks Zoltan

It works by clicking 'configre' and doing as you say. Clicking 'Add' obviously has issues.

I just counted my DB's and actually have 70+. New DB for each new client, some larger projects have their own DB.

SQLite is great when you have to import multiple xer's for claims etc. Can then easily forward DB to others.

 

Cheers

Laurent

Member for

6 years 2 months

Thanks Zoltan

It works by clicking 'configre' and doing as you say. Clicking 'Add' obviously has issues.

I just counted my DB's and actually have 70+. New DB for each new client, some larger projects have their own DB.

SQLite is great when you have to import multiple xer's for claims etc. Can then easily forward DB to others.

 

Cheers

Laurent

Member for

16 years 3 months

P6 lets you create 50 databases why do you need so many ?

There is a Workaround:

To create more than 50 database aliases by selecting 'Configure' at the P6 Professional login screen, and entering a new 'Database Alias' name.