Thank for the reply. I have verified both the Window and P6 for decimal and digit. After that, I tried to export P6 again but it still didn't work. Perhap the decimal and digit was not the cause for the exporting problem.
[[wysiwyg_imageupload:6885:]]
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Fri, 2019-07-19 14:47
Issue is caused by the Windows Regional Settings having an inconsistent Decimal symbol and Digit grouping symbol then the Decimal Symbol and Digit grouping symbol in P6 Professional.
To ensure that Decimal symbol and Digit grouping symbol for both P6 Professional and the Windows Region and Language settings, under Customize Format, match and are consistent with the desired currency please do the following:
Make sure that these match
For the Windows OS Region and Language settings:
Launch the Windows OS Control Panel
Select 'Region'
Select 'Additional Settings'
Select the 'Currency' tab
Review the 'Decimal symbol' and 'Digit grouping symbol'
For P6 Professional
Access P6 Professional
Select 'Currencies' under the 'Admin' menu item
Review the 'Decimal symbol' and 'Digit grouping symbol'make sure that
Member for
16 years 3 monthsglad that I coud help you
glad that I coud help you
Member for
6 years 3 monthsDear sỉ,Trying this way has
Dear sỉ,
Trying this way has solved the issues.
DQK
Member for
16 years 3 monthsgo to edit users
go to edit users prefernces
then on tthe time units tab under Units format uncheck Sub-unit
and also under Durations format uncheck sub-units
Member for
6 years 3 monthsDear Zoltan,Thank for the
Dear Zoltan,
Thank for the reply. I have verified both the Window and P6 for decimal and digit. After that, I tried to export P6 again but it still didn't work. Perhap the decimal and digit was not the cause for the exporting problem.
[[wysiwyg_imageupload:6885:]]
Member for
16 years 3 monthsIssue is caused by the
Issue is caused by the Windows Regional Settings having an inconsistent Decimal symbol and Digit grouping symbol then the Decimal Symbol and Digit grouping symbol in P6 Professional.
To ensure that Decimal symbol and Digit grouping symbol for both P6 Professional and the Windows Region and Language settings, under Customize Format, match and are consistent with the desired currency please do the following:
Make sure that these match
For the Windows OS Region and Language settings:
For P6 Professional