schedule comparison - can´t read projects on the SQLite db

Member for

13 years 11 months

Hi Santosh,

thanks for the reply.

Apparently no issues with the DB. I can work without problems with any of the SQLite DBs converted from v.17 to v.18 and the ones created directly with the v.18 version.

Only issue is with the importing of MSproject files, I receive an error with many XML. Patching didn´t solve it. From the import log: [···] Failed to load type for module CommandLineModule. Error was: An exception occurred while initializing module 'CommandLineModule'. [···] Information Exception Exception trying to load global data for Calendar: System.FormatException: String was not recognized as a valid DateTime. [···]

 

Member for

20 years 6 months

Is it a Database version issue? Connect to the SQLite DB using the latest P6 Professional client - do you receive an error message about versions?