Submitted by uxmanghani108 on Thu, 2019-06-20 08:17
Right Click on the Resource Assignment Sheet and clink on "Spreadsheet Options". Check on "Calculate Average". and Put the Value which will divide your Budgeted Units into Manpower. Means if your Time Scale is set in Days then simply Write "10" in "Divide Interval Totals by". it will give you Manpower on Daily basis. Simply you can convert your Budgeted Units into Manpower in Monthly Time Scale by Dividing "300".
you can simply Select All & Copy resources from Resource Assignment in Primevera and Paste into your Excel Sheet.
Member for
16 years 3 monthsMuhammid has the solution
Muhammid has the solution
Member for
21 years 8 monthsManaging your manpower using
Managing your manpower using averages frequently can result in not making available the necessary resources.
By clicking on the control bar at the bottom of the presentation you can make it full screen as well as you can manually control when each slide moves.
Member for
7 yearsWhat is the logic behind
What is the logic behind dividing budgeted unit by 10 or 300 ?????
Member for
10 years 6 monthsDear Usman,Right Click on the
Dear Usman,
Right Click on the Resource Assignment Sheet and clink on "Spreadsheet Options". Check on "Calculate Average". and Put the Value which will divide your Budgeted Units into Manpower. Means if your Time Scale is set in Days then simply Write "10" in "Divide Interval Totals by". it will give you Manpower on Daily basis. Simply you can convert your Budgeted Units into Manpower in Monthly Time Scale by Dividing "300".
you can simply Select All & Copy resources from Resource Assignment in Primevera and Paste into your Excel Sheet.
[[wysiwyg_imageupload:6867:]]
[[wysiwyg_imageupload:6868:]]
Hope this will solve your Issues.
Regards
Bilal (Pakistan)