Oracle Primavera - PM6 Member for 9 years 6 months Member for 9 years 6 months Submitted by roycdn on Thu, 2019-06-06 16:51 Permalink Thanks for the info I am Thanks for the info I am exporting the project and then opening to see if it rids me of the bad dates Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2019-06-06 14:09 Permalink go to admin Prefernces then go to admin Prefernces then Data limits then change the Maximum baslines per project to whatever number that you want. You can also change the number of Maximum baselines coped with project to whtaever you want. Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Thu, 2019-06-06 02:13 Permalink When resource leveling a When resource leveling a small schedule variance of an activity can become a cause for substantial rearrangements in the project network, it can change critical path or order of activities. Out of sequence progress can have a similar effect. Log in or register to post comments
Member for 9 years 6 months Member for 9 years 6 months Submitted by roycdn on Thu, 2019-06-06 16:51 Permalink Thanks for the info I am Thanks for the info I am exporting the project and then opening to see if it rids me of the bad dates
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2019-06-06 14:09 Permalink go to admin Prefernces then go to admin Prefernces then Data limits then change the Maximum baslines per project to whatever number that you want. You can also change the number of Maximum baselines coped with project to whtaever you want.
Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Thu, 2019-06-06 02:13 Permalink When resource leveling a When resource leveling a small schedule variance of an activity can become a cause for substantial rearrangements in the project network, it can change critical path or order of activities. Out of sequence progress can have a similar effect.
Member for
9 years 6 monthsThanks for the info I am
Thanks for the info
I am exporting the project and then opening to see if it rids me of the bad dates
Member for
16 years 3 monthsgo to admin Prefernces then
go to admin Prefernces
then Data limits
then change the Maximum baslines per project to whatever number that you want.
You can also change the number of Maximum baselines coped with project to whtaever you want.
Member for
21 years 8 monthsWhen resource leveling a
When resource leveling a small schedule variance of an activity can become a cause for substantial rearrangements in the project network, it can change critical path or order of activities.
Out of sequence progress can have a similar effect.