Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2019-05-31 13:37 Permalink add a labor resource export add a labor resource export both to excel copy the non labor data values to the labor resource import the excel file deleted the non labor resource done Log in or register to post comments