I have found the method to work with the WBS. In the grouping window select WBS and then turn off Indent and select the level to start on. If you need a second level add WBS again and select the next level to add to the grouping.
We created a wbs what made it down to the system level and then the piping line level. These are the ones I would like to see the tasks grouped and sorted by.