Thanks for the reply. I was just asking where the option to select Code or Coding is as when i right click above the numbers on the left handside this does not come up as an option in MSP
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2019-08-13 13:32
resolved this issue last week. There were lines of hidden coding in the MSP files which were preventing the import. I'm guessing that these would have prevented an MPX import too. Anyone having issues in the future try right clicking above the numbering on the lefthand side, select coding and delete the codes. Don't delete the columns - just the code and then it should import fine.
Hi Stacey, I'm experiencing a similar problem at the moment, could you elaborate on how you fixed it please as i cant seem to find the coding tab you mention anywhere!!
Thanks
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Mon, 2019-04-22 14:18
I've receievd a few PM's on this so thought I'd provide an update. I actually resolved this issue last week. There were lines of hidden coding in the MSP files which were preventing the import. I'm guessing that these would have prevented an MPX import too. Anyone having issues in the future try right clicking above the numbering on the lefthand side, select coding and delete the codes. Don't delete the columns - just the code and then it should import fine.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Fri, 2019-04-12 13:27
Member for
16 years 3 monthswhen she says codes I think
when she says codes I think she means things like a wbs code or somthing not TRUE coding
Member for
9 years 10 monthsHi Zoltan, Thanks for the
Hi Zoltan,
Thanks for the reply. I was just asking where the option to select Code or Coding is as when i right click above the numbers on the left handside this does not come up as an option in MSP
Member for
16 years 3 monthsJoel She Said resolved this
Joel She Said
resolved this issue last week. There were lines of hidden coding in the MSP files which were preventing the import. I'm guessing that these would have prevented an MPX import too. Anyone having issues in the future try right clicking above the numbering on the lefthand side, select coding and delete the codes. Don't delete the columns - just the code and then it should import fine.
Member for
9 years 10 monthsHi Stacey, I'm experiencing a
Hi Stacey, I'm experiencing a similar problem at the moment, could you elaborate on how you fixed it please as i cant seem to find the coding tab you mention anywhere!!
Thanks
Member for
16 years 3 monthsabove what number the line
above what number the line number. It just opens the detail for the activity. Are you refering to the Custom Fields tab ?
Member for
6 years 7 monthsHi guys,I've receievd a few
Hi guys,
I've receievd a few PM's on this so thought I'd provide an update. I actually resolved this issue last week. There were lines of hidden coding in the MSP files which were preventing the import. I'm guessing that these would have prevented an MPX import too. Anyone having issues in the future try right clicking above the numbering on the lefthand side, select coding and delete the codes. Don't delete the columns - just the code and then it should import fine.
Member for
16 years 3 monthsI sent you an email her check
I sent you an email her check it
Member for
21 yearsStacey,Collabro's Legare
Stacey,
Collabro's Legare always works. It converts anything, even MSP, to P6.
Member for
6 years 7 monthsCould you reccommend any
Could you reccommend any conversion tools for converting msp to mpx?
Member for
6 years 7 monthsHi ZoltanThank you for your
Hi Zoltan
Thank you for your reply. Unfortunately I don't have the option to save as an mpx file only xml.
Member for
16 years 3 monthsas a work around save these
as a work around save these as mpp then convert the mpp to an mpx and then import the mpx inot p6