Hi,

thank you for your suggestion, but I need to create different projects (with no activities), with different values for fields as project udfs or project codes. I would like to create a unique file with all projects in order to import it only once. I know that is just a dream. =S I tried with parser, but it is difficult to modify. 

 

Thanks.

Member for

20 years 6 months

There is no batch feature, but you can select multiple projects at a time and copy and paste them.

So 1 copy = 2 projects

then 4, then 8, then 16, 32, then 64 etc..