Lag and Original Duration

Member for

16 years 3 months

Santosh has the solution

Member for

20 years 6 months

  1. Open the project
  2. Select FILE>EXPORT>XLS
  3. Select both Activities and Activity Relationships
  4. The default Export template should be sufficient for what you need
  5. Select a locaiton to export the XLS file to
  6. Open the XLS file
  7. There is one tab for the activity infomration where you'll find duraton
  8. There is a second tab that lists all Relationships inlcuding lags
  9. Use VLOOUP to match the predecessor ID in the relationships tab to the duration in the activity tab

Member for

15 years 9 months

Hi Larry

You can use the 'Reports' feature for all the relationships in the schedule. Also the lags.

Go to Tools < reports and then select report AD-02 activity relationships.

Regards Johannes