Updating a MPX file

Member for

16 years 3 months

option #1

open the project in p6 then you can select ADD to existing 

option #2

if you have p3 or sure track convert the file from msp to either p3 or suretrack

then you can import the p3 project and use the update existing project option

 

Member for

9 years 6 months

Thanks, I'll do option 2 as I can import the file and then export as a xer and then do the update on the original file