Thanks, This is a what if scenario with a copy of the sch.
If I show the Late Bar and the project has a must finish on constraint, it gets me what I need, the lastest I can start and still finish on the required date. I know what goes against logic because of delays and outside influences, but it does calc the must start on date to meet must finish on date....
Jeff
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Mon, 2019-02-11 15:34
just put in the project must finish by date and schedule. Then it will tell you how far behind you are. Then change the start of the Project to match the Late Start date
Member for
16 years 3 monthsthats why I suggested it
thats why I suggested it
Member for
15 years 11 monthsAnother suggestion... Set the
Another suggestion... Set the Must Finish Date of the Project then assign As Late as Possible (ALAP) constraint to all the activities.
Member for
7 yearsThanks, This is a what if
Thanks, This is a what if scenario with a copy of the sch.
If I show the Late Bar and the project has a must finish on constraint, it gets me what I need, the lastest I can start and still finish on the required date. I know what goes against logic because of delays and outside influences, but it does calc the must start on date to meet must finish on date....
Jeff
Member for
16 years 3 monthsjust put in the project must
just put in the project must finish by date and schedule. Then it will tell you how far behind you are. Then change the start of the Project to match the Late Start date