How can I Schedule from a known finish date backwards....

Member for

16 years 3 months

thats why I suggested it 

Member for

15 years 11 months

Another suggestion... Set the Must Finish Date of the Project then assign As Late as Possible (ALAP) constraint to all the activities.

Member for

7 years

Thanks,  This is a what if scenario with a copy of the sch.

 

If I show the Late Bar and the project has a must finish on constraint, it gets me what I need, the lastest I can start and still finish on the required date.  I know what goes against logic because of delays and outside influences, but it does calc the must start on date to meet must finish on date....

 

 

Jeff

Member for

16 years 3 months

just put in the project must finish by date and schedule. Then it will tell you how far behind you are. Then change the start of the Project to match the Late Start date