Scott has the best answer, open both projects. Then view by WBS, each project will be organised within its own WBS Group (As the Proejct ID is the first level of the WBS also). Then you can just copy and paste, or cut and paste/drag if you need to, between the projects.
Member for
20 years 7 months
Member for20 years7 months
Submitted by Scott Hastie on Wed, 2019-01-16 16:48
Member for
16 years 3 monthsthat is the correct answer
that is the correct answer via WBS
Member for
20 years 6 monthsScott has the best answer,
Scott has the best answer, open both projects. Then view by WBS, each project will be organised within its own WBS Group (As the Proejct ID is the first level of the WBS also). Then you can just copy and paste, or cut and paste/drag if you need to, between the projects.
Member for
20 years 7 monthsI do this on a monthly
I do this on a monthly basis. I just open both projects in P6, and then copy the WBS's with the activities I need over to the other project.
Or, just simply open both projects, and highlight and copy the activities you want, then paste where you want them in the other project,