Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2019-01-10 13:47 Permalink what you can is to run a what you can is to run a global change to make the duration % complete equal to the physcial % complete go to tool global change New where Percent Complete Type equals Physical then duration % complete = Physical % complete now on the rigth select Change then on the botton right select Commit Changes Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2019-01-10 13:47 Permalink what you can is to run a what you can is to run a global change to make the duration % complete equal to the physcial % complete go to tool global change New where Percent Complete Type equals Physical then duration % complete = Physical % complete now on the rigth select Change then on the botton right select Commit Changes
Member for
16 years 3 monthswhat you can is to run a
what you can is to run a global change to make the duration % complete equal to the physcial % complete
go to tool global change
New
where Percent Complete Type equals Physical
then duration % complete = Physical % complete
now on the rigth select Change
then on the botton right select Commit Changes