the first part of ALL wbs structure is ALWAYS the name of the Project ID this is what makes the activity id unique so that you can link different projects together that have the same activity id.
If the activities are already in there then just export them with the correct wbs
if the activites are not in there but the wbs is the easiest way to do this change the name of the projet to a single letter like the letter M
then when you add the activity the wbs will be M.whatever
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
15 years 9 monthsThanks Zoltan. !
Thanks Zoltan. !
Member for
16 years 3 monthsthe first part of ALL wbs
the first part of ALL wbs structure is ALWAYS the name of the Project ID this is what makes the activity id unique so that you can link different projects together that have the same activity id.
If the activities are already in there then just export them with the correct wbs
if the activites are not in there but the wbs is the easiest way to do this change the name of the projet to a single letter like the letter M
then when you add the activity the wbs will be M.whatever
hope this helps