Raymund.
I have calculated this daily budgeted cost from Resource assignment. Then on excel I have done copy and paste. Then added the all budgeted cost. After that divided daily budgeted cost with the total one. And after that I took cummulative budgeted cost too..
But my schedule % calculation is different by 2 or 3 from the primavera schedule percentages.
And unfortunately Unbale to track the fault.entire schudule is resource added.
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Wed, 2018-12-26 09:07
That's easy, I mean if you were referring to "planned % complete" (meaning - baseline % complete). You can do that automatically anyway you want. Of course you have to move data date at anytime you want, which means that your schedule is progressing exactly as planned. Your "planned dates" shall automatically become "actual dates", everytime you update or move your data date. You can generate a tabular report, showing daily, weekly, monthly or whatever you want.
Thank you Anoon,
how would we know all the schedule % complete at a time corresponding to planned dates ?
My project start date is 3 January. And I want to know the schedule% complete for each day. In order to know this I am changing the data date each time and then scheduling it to see the % complete, which is a long procedure. Any shortcut for this ?
Member for
16 years 3 monthswhats your measuing stick ?
whats your measuing stick ? Manhours, dollars units ? or do you not have any.
Member for
15 years 11 monthsSet the data date at the end
Set the data date at the end of the working day.
Member for
9 years 3 monthsRaymund. I have calculated
Raymund.
I have calculated this daily budgeted cost from Resource assignment. Then on excel I have done copy and paste. Then added the all budgeted cost. After that divided daily budgeted cost with the total one. And after that I took cummulative budgeted cost too..
But my schedule % calculation is different by 2 or 3 from the primavera schedule percentages.
And unfortunately Unbale to track the fault.entire schudule is resource added.
Member for
15 years 11 monthsHi..Divide the Daily Budgeted
Hi..
Divide the Daily Budgeted Cost by the Project Total Cost then multiply by 100%.
That shows the Daily Schedule % Complete.
Member for
19 years 1 monthThat's easy, I mean if you
That's easy, I mean if you were referring to "planned % complete" (meaning - baseline % complete). You can do that automatically anyway you want. Of course you have to move data date at anytime you want, which means that your schedule is progressing exactly as planned. Your "planned dates" shall automatically become "actual dates", everytime you update or move your data date. You can generate a tabular report, showing daily, weekly, monthly or whatever you want.
Member for
9 years 3 monthsThank you Anoon, how would
Thank you Anoon,
how would we know all the schedule % complete at a time corresponding to planned dates ?
My project start date is 3 January. And I want to know the schedule% complete for each day. In order to know this I am changing the data date each time and then scheduling it to see the % complete, which is a long procedure. Any shortcut for this ?
Member for
19 years 1 monthYes, if you're planning unit
Yes, if you're planning unit is "day", then for sure you will get your corresponding percent complete per day.