Now this becomes interesting. Adab, comparing baselines and current schedules need to be consistent (consistency is the key). Though of course there will always be some details to vary, as plans don't always turn out exactly the way you planned them. Just be careful with the settings (I mean "Retained Logic" vs. "Progress Override", I guess you already knew how and where to use them?).
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2018-12-11 13:29
If the changes are only in baseline and not in current Program, probably you would be comparing Programs with different logic, duration, productivity resources etc.
Is there a problem with removing or detaching your baseline and do the editing as a stand-alone schedule, and then assign it back to your current or working schedule whenever you want? Well, I guess you need to make sure first that your baseline is the exact copy of your current schedule whenever you attach or detach it. Exact copy means: exact number of activities and descriptions. Of course other details may vary depending on how your plan is progressing actually.
Member for
16 years 3 monthsI told you how to detach a
I told you how to detach a schedule nothing fake about that
Member for
19 years 1 monthAdab, Tip: Don't always
Adab, Tip: Don't always believe in everything you read, especially if the source is unreliable. Nowadays "fake news" are rampant. Beware!
Member for
16 years 3 monthsyes NEVER use progress over
yes NEVER use progress over ride
Member for
19 years 1 monthNow this becomes interesting.
Now this becomes interesting. Adab, comparing baselines and current schedules need to be consistent (consistency is the key). Though of course there will always be some details to vary, as plans don't always turn out exactly the way you planned them. Just be careful with the settings (I mean "Retained Logic" vs. "Progress Override", I guess you already knew how and where to use them?).
Member for
16 years 3 monthsreverse the way that you
reverse the way that you attached it
select project
then assign baseline
then under Project Baseline select <Current Project> as the baseline
als under User Baseline
Primary select <Current Project> as the baseline
select OK
next under project select Maintain Baselines
highlight the scheduel that is listed there and on the rigth select Restore
Member for
17 years 4 monthsHi Abad,If the changes are
Hi Abad,
If the changes are only in baseline and not in current Program, probably you would be comparing Programs with different logic, duration, productivity resources etc.
BR
Kannan
Member for
19 years 1 monthIs there a problem with
Is there a problem with removing or detaching your baseline and do the editing as a stand-alone schedule, and then assign it back to your current or working schedule whenever you want? Well, I guess you need to make sure first that your baseline is the exact copy of your current schedule whenever you attach or detach it. Exact copy means: exact number of activities and descriptions. Of course other details may vary depending on how your plan is progressing actually.