I guess I have fixed it now.
For this I have taken the following three actions.
Probably anyone of these three actions have brought me on the right track.
1. I reduce the price per unit of each resources to 1$/ unit.
2. Many of the equipments' last activities were not having successor . So I assigned a successor.
3. All of the equipment's first activity were sharing same predecessor despite of having internal links between them. So removed all the predecessor except few leading equipments.
May anyone of the above worked for me.
Thank you so much for your support.
Member for
8 years 7 months
Member for8 years7 months
Submitted by Sultan Salabat Ahmed on Fri, 2018-12-07 07:48
Member for
16 years 3 monthsEVERY activity in the
EVERY activity in the schedule MUST have a successor except the last one.
Member for
9 years 3 monthsI guess I have fixed it
I guess I have fixed it now.
For this I have taken the following three actions.
Probably anyone of these three actions have brought me on the right track.
1. I reduce the price per unit of each resources to 1$/ unit.
2. Many of the equipments' last activities were not having successor . So I assigned a successor.
3. All of the equipment's first activity were sharing same predecessor despite of having internal links between them. So removed all the predecessor except few leading equipments.
May anyone of the above worked for me.
Thank you so much for your support.
Member for
8 years 7 monthsFor Schedule % Percent
For Schedule % Percent completion, Check following
1. Make sure your data date is valid
2. Your baseline must be assigned.
However, for WBS, cost must be assigned to activites.
Check above points and schedule again by pressing F9.
Member for
8 years 7 monthsFor Schedule % Percent
For Schedule % Percent completion, Check following
1. Make sure your data date is valid
2. Your baseline must be assigned.
However, for WBS, cost must be assigned to activites.
Check above points and schedule again by pressing F9.
Member for
9 years 3 monthsYes I change the data date.
Yes I change the data date.
Member for
9 years 3 monthsI am using duration type.
I am using duration type.
Member for
16 years 3 monthsdud you update teh schedule
dud you update teh schedule ?
if you did update it what % complete type are you using ?
did you change the data date ?