EVERY activity in the schedule MUST have a successor except the last one. 

Member for

9 years 3 months

I guess I have fixed it now.
For this I have taken the following three actions.
Probably anyone of these three actions have brought me on the right track.

1. I reduce the price per unit of each resources to 1$/ unit.
2. Many of the equipments' last activities were not having successor . So I assigned a successor.
3. All of the equipment's first activity were sharing same predecessor despite of having internal links between them. So removed all the predecessor except few leading equipments.

May anyone of the above worked for me.

Thank you so much for your support.

Member for

8 years 7 months

For Schedule % Percent completion, Check following

1. Make sure your data date is valid

2. Your baseline must be assigned. 

However, for WBS, cost must be assigned to activites.

Check above points and schedule again by pressing F9.

Member for

8 years 7 months

For Schedule % Percent completion, Check following

1. Make sure your data date is valid

2. Your baseline must be assigned. 

However, for WBS, cost must be assigned to activites.

Check above points and schedule again by pressing F9.

Member for

16 years 3 months

dud you update teh schedule ?

if you did update it what % complete type are you using ?

did you change the data date ?