Hi,

For the performance %, you have to assign cost (as a weight factor or as per BOQ) in order to calculate the earned value.

BR

Kannan

Member for

9 years 3 months

But in some of my project I am getting performance %. Literally I tried a lot but not able to understand the ligic behind this usage.
Thanks anyways.

Member for

16 years 3 months

you have to use physical % complete