Activity Name in ALL CAPS

Member for

7 years

Thanks, Steven....

 

I appreciate the suggestion.  Will give it a try.

 

Jeff

Member for

8 years 1 month

Managed to check & unfortunately this is not one of the string functions available in the global change, so would need to do it through excel.

Steven

Member for

16 years 3 months

Steven has it correct but I woul like to add that adny new activites that you ADD to the schedule make them lower case or initial caps so that you know it a change order or ithat this activity ws not in the original basline schedule 

Member for

12 years 6 months

Hello Steve,

Could you please help me sharing the coding or parameter setting for Global change of all Caps or vice versa in P6.

Member for

8 years 1 month

Jeff,

Easiest way I can think of is to export the tasks to excel, add a column at the end & use the =UPPER(A3) formula (where cell A3 is the first task description.

Copy this formula down for all rows, then re-select and copy this column, go to cell A3 then right click & paste values.

Re-select the calculated column then clear contents.

Re-import the excel version of the plan.

If you are working on a large schedule, make sure that you export the minimum amount of columns to speed up the export / import process.

You may be able to do this with a global change within Primavera, however not in front of my computer to test.

Hope this helps

Steven