Oracle Primavera - PM6 Member for 8 years 1 month Member for 8 years 1 month Submitted by StevenA on Thu, 2018-11-08 18:01 Permalink I’m guessing that the bottom I’m guessing that the bottom image is looking at the remaining units. The activity you have selected is complete, so the remaining labour units will be zero. The 32 man hours is budgeted (originally planned) labour units (and 32 hours actual labour units). Any activity marked as complete will have zero hours remaining labour units. Regards, Steven Log in or register to post comments
Member for 8 years 1 month Member for 8 years 1 month Submitted by StevenA on Thu, 2018-11-08 18:01 Permalink I’m guessing that the bottom I’m guessing that the bottom image is looking at the remaining units. The activity you have selected is complete, so the remaining labour units will be zero. The 32 man hours is budgeted (originally planned) labour units (and 32 hours actual labour units). Any activity marked as complete will have zero hours remaining labour units. Regards, Steven
Member for
8 years 1 monthI’m guessing that the bottom
I’m guessing that the bottom image is looking at the remaining units.
The activity you have selected is complete, so the remaining labour units will be zero.
The 32 man hours is budgeted (originally planned) labour units (and 32 hours actual labour units).
Any activity marked as complete will have zero hours remaining labour units.
Regards,
Steven