I’m guessing that the bottom image is looking at the remaining units.

The activity you have selected is complete, so the remaining labour units will be zero.

The 32 man hours is budgeted (originally planned) labour units (and 32 hours actual labour units).

Any activity marked as complete will have zero hours remaining labour units.

Regards,

Steven