Sometimes, the issues is that the export is complete and the Dialog box has disappeared off screen - are you using multiple monitors?
If this is the case, you need to give enough time for the export to finish, a few minutes should be enough, don't click or move the mouse during this time. When the few minutes are complete, press the spacebar - this is the same as clicking on the "OK" buttong that shows after export is complete.
If the above works, and you are using multiple monitors, try chaing the primary monitor, or switch to using a single display and try again.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Wed, 2018-09-19 14:10
Member for
16 years 3 monthsno answers ?
no answers ?
Member for
20 years 6 monthsSometimes, the issues is that
Sometimes, the issues is that the export is complete and the Dialog box has disappeared off screen - are you using multiple monitors?
If this is the case, you need to give enough time for the export to finish, a few minutes should be enough, don't click or move the mouse during this time. When the few minutes are complete, press the spacebar - this is the same as clicking on the "OK" buttong that shows after export is complete.
If the above works, and you are using multiple monitors, try chaing the primary monitor, or switch to using a single display and try again.
Member for
16 years 3 monthswhat is it that you are
what is it that you are trying to export to excel ? as a test just eport activities and in the export just filter for 1 activity.
is excel a 64 or 32 based application ?
what version is excel ?