Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2018-08-16 14:15 Permalink why not just work with the why not just work with the same live project for every update. When you are done updating copy that file and save that copy as a historical record. This way you are always working in the same file with the correct links to and from different projects. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2018-08-16 14:15 Permalink why not just work with the why not just work with the same live project for every update. When you are done updating copy that file and save that copy as a historical record. This way you are always working in the same file with the correct links to and from different projects.
Member for
16 years 3 monthswhy not just work with the
why not just work with the same live project for every update. When you are done updating copy that file and save that copy as a historical record.
This way you are always working in the same file with the correct links to and from different projects.