insert the delay as a new actviity into the CURRENT schedule that was in effect during the time of he delay. Make sure the successor is the activity that has been delayed. If there is a predecessor then assign the predecessor if not use a constraint date or an actual date to tie the front end of the activity. Make the activity name in ALL CAPS so that it stands out make sure to include the work DELAY in the activity description. Also create a new activity code you can call it DELAYS and give it a code value of July18. Then assign this code vlaue to the delay activity and its predecessor and immediate successor.
You can use this technique for future delays. Let's say you experience another delay is September then add the code value under the DELAYS code as Sep18
and so
Make sure to include an Analysis in narrative format of what you have done to the schedule and how the delay has impacted the completion date. Make sure to state what type of delay it is (whos fault) and if it is a compensable or non compensable delay.
Member for
16 years 3 monthsinsert the delay as a new
insert the delay as a new actviity into the CURRENT schedule that was in effect during the time of he delay. Make sure the successor is the activity that has been delayed. If there is a predecessor then assign the predecessor if not use a constraint date or an actual date to tie the front end of the activity. Make the activity name in ALL CAPS so that it stands out make sure to include the work DELAY in the activity description. Also create a new activity code you can call it DELAYS and give it a code value of July18. Then assign this code vlaue to the delay activity and its predecessor and immediate successor.
You can use this technique for future delays. Let's say you experience another delay is September then add the code value under the DELAYS code as Sep18
and so
Make sure to include an Analysis in narrative format of what you have done to the schedule and how the delay has impacted the completion date. Make sure to state what type of delay it is (whos fault) and if it is a compensable or non compensable delay.