All activities in question are Task Dependent, Fixed Duration & Units (and tested as Fixed Duration & Units/Time), Physical % Complete Type, with no contraints or levelling applied.
Any other ideas? My current work around is checking if the durations have moved with global changes into UDFs and adjusting accordingly. Though it'd be nice to understand why they're changing in the first instance.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Mon, 2018-07-16 14:38
The duration type was set on 'Fixed Duration & Units', though when testing it as 'Fixed Druation and Unit/Time' I get a similar result.
Oddly enough, sample testing the changes under 1 WBS with 9 activities - 3 of the activities duration change whilst the others remain the same when the calendar is changed between 5d blockout vs 5d standard. The remaining 6 activities seem to have similar attributes..so I'm still at a loss as to why this is occuring.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Fri, 2018-07-13 13:41
Member for
10 years 3 monthsAll activities in question
All activities in question are Task Dependent, Fixed Duration & Units (and tested as Fixed Duration & Units/Time), Physical % Complete Type, with no contraints or levelling applied.
Any other ideas? My current work around is checking if the durations have moved with global changes into UDFs and adjusting accordingly. Though it'd be nice to understand why they're changing in the first instance.
Member for
16 years 3 monthsmake sure that the activity
make sure that the activity type is task and not resource
Member for
10 years 3 monthsThanks Zoltan,The duration
Thanks Zoltan,
The duration type was set on 'Fixed Duration & Units', though when testing it as 'Fixed Druation and Unit/Time' I get a similar result.
Oddly enough, sample testing the changes under 1 WBS with 9 activities - 3 of the activities duration change whilst the others remain the same when the calendar is changed between 5d blockout vs 5d standard. The remaining 6 activities seem to have similar attributes..so I'm still at a loss as to why this is occuring.
Member for
16 years 3 monthswhat is your duration type
what is your duration type set to ? Use fixed duration and units/time and you will not have this problem