I would agree with Zoltan's last comment! It is unlikely that they were all started & completed exactly as per plan.
For only 50 activities, I would just update manually so that you can update the start & finish dates / times as required.
Depending on the size of the Turnaround & the level of detail in the plan, it is likely that you will need to update more than this most days & they will not all be the same trades so not as easy to filter.
How you capture progress during the Turnaround is critical in how long this takes to complete each day, so worth spending time getting this right before the Turnaround starts.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Wed, 2018-06-27 15:30
option #1 export to excel and thne populate then import to p6
option #2
filter for all of the scaffolding activites and select
tools Update progress then select Selected activities only
the problem that you have with doing it this way is that it assumes that all of the scaffolding in this filter started and completed on schedule (that NEVER happens)
Member for
8 years 1 monthI would agree with Zoltan's
I would agree with Zoltan's last comment! It is unlikely that they were all started & completed exactly as per plan.
For only 50 activities, I would just update manually so that you can update the start & finish dates / times as required.
Depending on the size of the Turnaround & the level of detail in the plan, it is likely that you will need to update more than this most days & they will not all be the same trades so not as easy to filter.
How you capture progress during the Turnaround is critical in how long this takes to complete each day, so worth spending time getting this right before the Turnaround starts.
Member for
16 years 3 monthsyou can do it 2 ways option
you can do it 2 ways
option #1 export to excel and thne populate then import to p6
option #2
filter for all of the scaffolding activites and select
tools Update progress then select Selected activities only
the problem that you have with doing it this way is that it assumes that all of the scaffolding in this filter started and completed on schedule (that NEVER happens)